August 27, 2009
Day 19, early report
Well, it’s 5:50 on Day 19, which was my hope to be finished. I can see the light at the end of the tunnel — I need to install the toilet, plumb the sinks, and install and caulk the backsplash and sidesplashes. I also need to do some touch-up paint on the walls and the ceiling; that may or may not happen tonight. I will also need to rehang the towel bars and doors. The last thing to do, which I was never considering part of the 19-day plan, is to re-install the baseboards. Dad will be back on Saturday and I’m borrowing a chop saw and air compressor/nail gun from a friend in order to do both the master bath and guest bath.
So, it might take a diet Coke in a little while, but I’m going to push through to try to complete it all tonight! Wish me luck!